[07-03-29] [08:48] by [Peter]
New resource found for Powersupply-engineering. Groundworks and initial material will be transfered in the upcoming week.

[07-01-03] [12:26] by [Peter]
Yearly report for 2006 is published externally.

[07-01-03] [12:25] by [Peter]
After database failure the external webpage is now up and running again.

[06-06-27] [07:34] by [Peter]
Not really news, but to let you know that we're still on track :) . We're still awaiting the estimates for manufacturing of playfield parts.

[06-03-30] [22:07] by [Peter]
All AutoCAD-drawing material for playfield mechanics has now been sent away for estimate of costs.

[06-01-27] [15:55] by [Peter]
Major change of involved persons in the audio team to be announced.

[06-01-17] [09:52] by [Peter]
New projectmanagement software found which better suits our need, expected to be implemented in the upcoming weeks.

[06-01-17] [09:51] by [Peter]
Businessplan subproject initiated.

[06-01-17] [09:50] by [Peter]
Weekly internal report distributed.

[06-01-10] [09:55] by [Peter]
Audio hardware subproject initiated.

[06-01-10] [09:54] by [Peter]
Goal timeframe for a finished draft Admin-interface set.

[06-01-10] [09:53] by [Peter]
Weekly internal report distributed.

[06-01-10] [09:53] by [Peter]
First Pin-cabinett prepared with Coin-interface and electronics. Fully functional in regards to this, all tests successful.

[06-01-01] [12:05] by [Peter]
Official yearly report published on webpage.

[05-12-18] [21:55] by [Peter]
Milestone setup to officially present parts of the prototype games earlier then previously planned.

[05-12-18] [21:54] by [Peter]
Work initated on the Swann Pinball Yearly Report.

[05-12-18] [21:54] by [Peter]
New backbox to Cabinet connection-appliance invented which will simplify in a revolutionary way for the operators.

[05-12-18] [21:51] by [Peter]
Weekly internal report distributed after the pause in project management due non-project related issues.

[05-11-15] [23:17] by [Peter]
Artwork and layout for the new external webpage presented internally. Work is currently in progress on texts and information.

[05-11-15] [23:15] by [Peter]
Weekly internal report distributed.

[05-11-15] [23:15] by [Peter]
Subproject initiated for testing of certain lightening electronics that are planned to be used in the game. Some lab-tests have to be made before we can fully put the ideas into the prototype products pipeline.

[05-11-15] [23:12] by [Peter]
Major decisions made in the Mechanical constructions team to finalize further details before hand-over to manufacture. This will delay construction of some parts and speed up for others.

[05-11-10] [09:01] by [Peter]
Internal planning for financing options are discussed and even considered necessary to enable building our product according to the lined out specifications.

[05-11-10] [08:57] by [Peter]
Systemspecifications for communication interface between powerdriver, lampdriver, switchmatrix and powersupply unit is partially made and will be activly worked on under the upcomming month to enable the distributed workteam enviroment.

[05-11-10] [08:55] by [Peter]
Electronics engineering har been splitted up in four stages where stage one is almost ready for manufacturing. Stage two is finished in regards to simulations and on the drawing board but lacks lab setup before entering the manufacturing stage.
Stage three and four are briefly sketched out and needs more detailed work before going into drawing-stage.

[05-11-10] [08:52] by [Peter]
Due to illnesses and a very busy schedule, finally the weekly internal reports are starting up again.
Weekly internal report distributed.

[05-10-25] [21:19] by [Peter]
Programming initiated on the main core software system for the Pinball System.

[05-10-25] [21:18] by [Peter]
Additional Audiosequences composed and presented by the audioteam.

[05-10-25] [21:17] by [Peter]
Weekly internal report distributed.

[05-10-18] [22:06] by [Peter]
Minor fixes in AutoCAD-sketches for ramp construction finalized.

[05-10-18] [22:06] by [Peter]
Weekly internal report distributed.

[05-10-11] [10:25] by [Peter]
Work in progress to find an alternative project management online software that better fits our needs.

[05-10-11] [10:23] by [Peter]
Additional detailed drafts presented of playfield artwork.

[05-10-11] [10:22] by [Peter]
Hardware platform for Operating System development has been delivered to the programming team.

[05-10-11] [10:22] by [Peter]
Alternate version of Backglas artwork presented of the artwork team.

[05-10-11] [10:21] by [Peter]
Weekly internal report distributed.

[05-10-03] [09:50] by [Peter]
Weekly internal report distributed.

[05-10-03] [09:49] by [Peter]
New Server for internal storage installed succesfully.

[05-10-03] [09:48] by [Peter]
Project directions sketched out in regards to financing such as government subsidies and other similar funding alternatives.

[05-10-03] [09:44] by [Peter]
Currently we are talking to Airforce and Defence-industry companies to find suitable Electronics-parts that matches our high demands.

[05-09-27] [09:44] by [Peter]
Weekly internal report distributed.

[05-09-27] [09:44] by [Peter]
Hardware equipment for Software development platform recieved.

[05-09-27] [09:43] by [Peter]
An total re-editing of all current AutoCAD drawings is in progress to be able to present the material and get pricing from potential manufactors.

[05-09-20] [22:06] by [Peter]
Major rework is done on our internal projectmanagement/partsdatabase and forum webpages.

[05-09-20] [22:05] by [Peter]
AutoCAD drawing on detailed playfield initiated.

[05-09-20] [22:03] by [Peter]
Weekly internal report distributed.

[05-09-20] [22:03] by [Peter]
Hardware equipment for Software development platform ordered.

[05-09-13] [10:36] by [Peter]
First tests of mounting of Rack for Electronics in progress.

[05-09-13] [10:35] by [Peter]
Framework för Operating System sketched out.

[05-09-13] [10:34] by [Peter]
CPU-unit has now been specificed.

[05-09-13] [10:34] by [Peter]
Weekly internal report distributed.

[05-09-05] [21:07] by [Peter]
Final Electronics mainboard predesign is in the pipeline.

[05-09-05] [21:05] by [Peter]
Weekly internal report distributed.

[05-09-05] [21:04] by [Peter]
A major projectmanagement reorganization will take place under the upcoming weeks.

[05-09-05] [21:03] by [Peter]
Work has been initated to start building on the Prototype powersupplies.

[05-09-05] [21:02] by [Peter]
An professional Operasinger has been located that is willing to help as background chorus in audiorecordings.

[05-08-29] [12:32] by [Peter]
Weekly internal report distributed.

[05-08-29] [12:31] by [Peter]
Sponsorship of players in PAPA8 wore fruit. We can now warmly congratulate Helena Walter for winning first price in the B-Division!

[05-08-14] [02:51] by [Peter]
Swann Pinball activly sponsors Swedish players at the World Pinball Championships PAPA8.

[05-08-09] [08:50] by [Peter]
Three teammembers will be going to the PAPA (World championships in Pinball) competition in USA.

[05-08-09] [08:49] by [Peter]
Coinmech electronics fully functional for interfacing with Admin interface.

[05-08-09] [08:48] by [Peter]
Admin interface Hardware first prototype finalized. All tests sucessful.

[05-08-09] [08:46] by [Peter]
We welcome a new member to the team, David Kjellberg. He will be a welcomed needed resource taking care of project management and administration.

[05-08-09] [08:43] by [Peter]
Weekly internal report distributed.

[05-08-02] [17:05] by [Peter]
Drafts on artwork for several game characters presented.

[05-08-02] [17:04] by [Peter]
Several Multiball and Hurry-Up Audio sequences made.

[05-08-02] [17:02] by [Peter]
Specifications for interface for admin input presented for programming team.

[05-08-02] [17:02] by [Peter]
Weekly internal report distributed.

[05-07-25] [21:53] by [Peter]
An additional Super Wizard mode determined to be only known by the programming team. Certain audio-recording will have to be made seperatly to handle this.

[05-07-25] [21:52] by [Peter]
Weekly internal report distributed.

[05-07-25] [21:52] by [Peter]
PCB-layout for admin-interface well under progress.

[05-07-18] [22:54] by [Peter]
Testrigg's for admin user-interface in the works. These are to be used by the programming team to get a 1:1 enviroment without needing to simulate the communication.

[05-07-18] [22:52] by [Peter]
Weekly internal report distributed.

[05-07-18] [22:52] by [Peter]
First draft on final circuitry for admin and coin-mech electronics and PCB presented.

[05-07-16] [20:51] by [Peter]
Testbed coinmech circuitry fully functional.

[05-07-11] [22:28] by [Peter]
Weekly internal report distributed.

[05-07-11] [22:27] by [Peter]
Switchmatrix adjusted to reflect changes due to Admin-interface.

[05-07-04] [20:43] by [Peter]
Coin-door/Ticket-printer/Admin-keys unit parts has arrived, assembly of prototypes to be initiated.

[05-07-04] [20:41] by [Peter]
Marketingmaterial and ideas for an upcoming calendar in discussions.

[05-07-04] [20:40] by [Peter]
Online project management application pre-version installed.

[05-07-04] [20:39] by [Peter]
Weekly internal report distributed.

[05-06-28] [00:23] by [Peter]
Online project management application and Parts database update in development pipeline.

[05-06-28] [00:22] by [Peter]
Work in progress on new external webpage.

[05-06-28] [00:21] by [Peter]
Specifications för the Industrial connector for playfield electronics attachment presented. A preliminary connector selected.

[05-06-28] [00:19] by [Peter]
Weekly internal report distributed.

[05-06-28] [00:18] by [Peter]
Displayunit assembly specifications first draft presented.

[05-06-20] [22:45] by [Peter]
Weekly internal report distributed.

[05-06-20] [22:44] by [Peter]
Subproject started to enhance and simplify the project management.

[05-06-20] [22:43] by [Peter]
A major updating and rebuilding of the external webpage is now in the pipeline.

[05-06-20] [22:41] by [Peter]
Additional very valuable resources and help found in regards to printing of cabinet and playfield artworks.

[05-06-20] [22:38] by [Peter]
PCB-layout for the switchmatrix circuitry almost finished.

[05-06-12] [21:45] by [Peter]
Weekly internal report distributed.

[05-06-12] [21:44] by [Peter]
Coin-door/Ticket-printer/Admin-keys interface design initiated.

[05-06-12] [21:43] by [Peter]
Powerdriver PCB-layout finished.

[05-06-12] [21:42] by [Peter]
Ballarch artwork finalized.

[05-06-06] [12:12] by [Peter]
Display unit attachment standards specificed.

[05-06-06] [12:07] by [Peter]
Weekly internal report distributed.

[05-06-06] [00:35] by [Peter]
Work initiated on complete system specifications.

[05-06-06] [00:31] by [Peter]
Several Audio sequences presented from the audioteam.

[05-05-30] [23:04] by [Peter]
Work initiated on design for assembly construction for system component boards.

[05-05-30] [23:01] by [Peter]
Weekly internal report distributed.

[05-05-30] [22:40] by [Peter]
Major batch of AutoCAD-drawings for mechanical parts sent away for prototype making.

[05-05-30] [22:38] by [Peter]
First public presentation made on the NPC 2005 in Trondheim.

[05-05-26] [10:28] by [Daniel]
Artwork for public presentation is completed. Minor details from actual game included. (First public views will be at the NPC 2005).

[05-05-23] [15:22] by [Peter]
Weekly internal report distributed.

[05-05-23] [15:20] by [Peter]
Marketing presentation for public events in it's final drafts.

[05-05-23] [15:18] by [Peter]
Selection of appropriate formfactor for the main processing unit made.

[05-05-15] [23:54] by [Peter]
Weekly internal report distributed.

[05-05-15] [23:53] by [Peter]
Work in progress on switchmatrix logic PCB-layout.

[05-05-15] [23:51] by [Peter]
Selection of appropriate DIN-standards for connectors and attachments made.

[05-05-15] [23:44] by [Peter]
First drafts of final signalingprotocol between systemcomponents presented.

[05-05-15] [23:42] by [Peter]
Additional parts order details recieved.

[05-05-09] [10:44] by [Peter]
Weekly internal report distributed.

[05-05-09] [10:44] by [Peter]
Previously made parts order items recieved.

[05-05-09] [10:42] by [Peter]
Switchmatrix prototype hardware will recieve a software update this week with increased communication speed and added requested features.

[05-05-09] [10:41] by [Peter]
Standards for electronics design is now finalized and selected. Work is initiated on final circuit layouts for Switchmatrix and Powerdriver electronics based on these.

[05-05-09] [10:38] by [Peter]
All Autocad drawings for laneguides are expected to be finished and sent away for manufacture this week.

[05-05-09] [10:37] by [Peter]
First drafts presented of Cabinet (top box and main box). Autocad in progress. Major rework from the previous "standard" due to several needs in regards to electronics and mechanical design.

[05-05-09] [10:34] by [Peter]
The audioteam has presented a pre-version of the mainscore audiosequence.

[05-05-02] [23:29] by [Peter]
Weekly internal report distributed.

[05-05-01] [15:05] by [Peter]
Mechanical construction team has been expanded with an additional valuble resource. We welcome Tommy Andersson to the project.

[05-04-25] [12:38] by [Peter]
Admin user interface design finalized.

[05-04-25] [12:37] by [Peter]
Weekly internal report distributed.

[05-04-25] [12:36] by [Peter]
Swann Pinball will be doing a presentation about the Project on the Norwegian Pinball Convention 2005 in Trondheim, 28-29 May.

[05-04-18] [16:34] by [Peter]
Published article for Stockholm Pinball Yearbook on external webpage.

[05-04-18] [10:43] by [Peter]
Major parts order executed for basic items. An additional order is expected to be accomplished the following days.

[05-04-18] [08:19] by [Peter]
Weekly internal report distributed.

[05-04-17] [14:22] by [Peter]
Audioteam has been expanded with an additional valuble resource. We welcome Olof Gustafsson to the project.

[05-04-14] [21:01] by [Daniel]
Image gallery updated.

[05-04-14] [20:55] by [Daniel]
Ideas for specific cabinet artwork details presented.

[05-04-10] [22:34] by [Peter]
Weekly internal report distributed.

[05-04-10] [22:33] by [Peter]
Major mechanical construction first AutoCAD draft presented.

[05-04-10] [22:29] by [Peter]
Successful tests of magnetic field for special feature.

[05-04-10] [22:26] by [Peter]
Admin user interface design in progress. A preliminary version presented.

[05-03-28] [12:38] by [Peter]
Weekly internal report distributed.

[05-03-28] [01:20] by [Peter]
Draft presented on cabeling for power electronics.

[05-03-28] [01:16] by [Peter]
Design of circuitry for Powersupply presented (three months of solid work). Some additional simulations have to be done before entering the prototype-phase.

[05-03-25] [14:04] by [Peter]
Minor changes in lampmatrix to reflect changes in rulessheet.

[05-03-23] [22:52] by [Daniel]
First sketches on inserts-details Artwork finished.

[05-03-20] [23:35] by [Peter]
Weekly internal report distributed.

[05-03-20] [23:14] by [Peter]
Major updates made to parts database according to requests from the contruction team.

[05-03-20] [23:11] by [Peter]
Important change made in rulesheet that affects both hardware and software. All necessary documents has been updated to reflect this change.

[05-03-20] [23:07] by [Peter]
Several standard parts recieved and installed on whitewood playfield.

[05-03-20] [23:06] by [Peter]
CVS system up and running for version control and synchronized software development.

[05-03-19] [16:42] by [Peter]
Marketingmaterial recieved, additional items expected to be recieved in a couple of weeks.

[05-03-14] [18:18] by [Peter]
Weekly internal report distributed.

[05-03-14] [18:14] by [Peter]
Marketingmaterial ordered.

[05-03-14] [18:13] by [Peter]
Detailed walk-through of rulesheet in progress. Several minor changes executed.

[05-03-14] [18:12] by [Peter]
An additional miniplayfield has been built.

[05-03-06] [23:38] by [Peter]
Weekly internal report distributed.

[05-03-06] [23:38] by [Peter]
Switch-matrix alfa-version test software fully functional.

[05-03-03] [21:53] by [Peter]
Switchmatrix prototype connected to mini-playfield. All initial tests successfully executed.

[05-03-02] [09:57] by [Peter]
Online Parts database up and running. Beta-testing commenced.

[05-03-01] [00:03] by [Peter]
Work initiated on online complete parts-database.

[05-02-27] [22:34] by [Peter]
Weekly internal report distributed.

[05-02-27] [22:13] by [Peter]
Playfield inserts test-installation made for specifications and groundwork in regards to lamp-planning.

[05-02-26] [20:55] by [Peter]
Minor change made in current playfield design to minimize ball hangups and for future additional features.

[05-02-26] [20:53] by [Peter]
Drillmap first version finished.

[05-02-20] [22:51] by [Peter]
Weekly internal report distributed.

[05-02-20] [22:22] by [Peter]
Internal online Rulessheet created for easy browsing and cross-referencing.

[05-02-20] [22:21] by [Peter]
Major changes in lamp-matrix to adapt to alternative electronics design.

[05-02-20] [22:11] by [Peter]
Progress-report about powersupply unit delivered. All simulations sucessful and design outlines presented.

[05-02-17] [22:59] by [Peter]
Minor changes made in rules document to adjust for wiz-players.

[05-02-13] [23:58] by [Peter]
Weekly internal report distributed.

[05-02-13] [23:15] by [Peter]
Marketing materials designed. Procurement procedure in progress for these items.

[05-02-13] [23:13] by [Peter]
Initiated work on building an additional miniplayfield for the software development enviroment.

[05-02-09] [16:00] by [Peter]
Located manufacturer of inserts and other essential standard plastic-details.

[05-02-07] [00:34] by [Peter]
Weekly internal report distributed.

[05-02-06] [23:23] by [Peter]
Distributionsystem for logic software update successfully included into the hardware design.

[05-02-06] [23:22] by [Peter]
Encryption algorithm applied to hardware logic for reverse engineering protection.

[05-02-06] [23:19] by [Peter]
Work on the first draft of powersupply unit in progress. Advanced monitoring and voltage control from software will be available.

[05-02-06] [23:14] by [Peter]
Work in progress on final PCB layout. Logic and power design pre-specifications made.

[05-02-06] [23:11] by [Peter]
Testrig built with flipper driver electronics. All tests successfully executed.

[05-01-30] [23:33] by [Peter]
Weekly internal report distributed.

[05-01-30] [23:33] by [Peter]
Work on detailed specifications for the drillmap initiated.

[05-01-27] [22:11] by [Peter]
Essential prototype plastics built and attached to whitewood playfield.

[05-01-25] [21:14] by [Peter]
First playable whitewood prototype ramp built.

[05-01-24] [01:22] by [Peter]
Weekly internal report distributed.

[05-01-20] [22:13] by [Peter]
Initiated work on powersupply design. Located resources and material.

[05-01-20] [22:11] by [Peter]
Alpha version for Powerdriver electronics designed (revision 2).

[05-01-20] [22:08] by [Peter]
Alpha-version of Flipperdriver electronics made (revision 5). Fully playable for dual winding coils. All tests executed successfully.

[05-01-17] [21:27] by [Peter]
Backbox frame design-work initiated.

[05-01-17] [21:22] by [Peter]
Weekly internal report distributed.

[05-01-11] [02:18] by [Stefan]
A new image-gallery function added on the admin-page. The gallery is available at "images" on the menu.

[05-01-10] [00:30] by [Peter]
Weekly internal report distributed.

[05-01-09] [17:19] by [Peter]
First predesign of mainboard drawn.

[05-01-09] [17:18] by [Peter]
Switchmatrix prototype board finished.

[05-01-09] [17:09] by [Peter]
Guestbook online. Major rework is in progress with several additional features for the webpage.

[05-01-04] [23:10] by [Peter]
Alpha-version of Flipperdriver electronics made (revision 4).

[05-01-02] [23:32] by [Peter]
News-script fully functional on www.swannpinball.se web-site.

[05-01-02] [23:31] by [Peter]
Test-application for Flipperdriver electronics updated (now v0.4).

[05-01-02] [23:30] by [Peter]
First testball launched on Whitewood playfield.

[05-01-02] [23:29] by [Peter]
Four animation-drafts presented.

[05-01-02] [23:26] by [Peter]
Additional plastics artwork presented.

[04-12-31] [13:06] by [Peter]
Official yearly report published on webpage.

[04-12-28] [19:57] by [Peter]
Weekly internal report distributed.

[04-12-24] [10:40] by [Peter]
Cabinet front-art first draft presented.

[04-12-21] [19:09] by [Peter]
Switchmatrix bufferhandling and debouncing in it's final stages of development.

[04-12-21] [19:08] by [Peter]
First custom manufactured constructions installed on Whitewood playfield.

[04-12-19] [10:34] by [Peter]
Weekly internal report distributed.

[04-12-19] [10:32] by [Peter]
Backbox planning pre-designed.

[04-12-13] [10:25] by [Peter]
Minor changes in hardware for switchmatrix, new revision version 0.2 .

[04-12-13] [10:23] by [Peter]
Weekly internal report distributed.

[04-12-06] [09:15] by [Peter]
Switchmatrix buffer and debouncing logic programming in progress.

[04-12-06] [09:13] by [Peter]
Weekly internal report distributed.

[04-12-06] [09:12] by [Peter]
New webpage online on www.swannpinball.se

[04-12-06] [09:11] by [Peter]
First Powersupply specifications made.

[04-12-06] [09:09] by [Peter]
Test-application for Flipperdriver electronics created.

[04-11-29] [09:40] by [Peter]
Weekly internal report distributed.

[04-11-29] [09:40] by [Peter]
First studio recordings for audio-sequences made.

[04-11-29] [09:39] by [Peter]
Basic switchmatrix scanning tests successfully executed.

[04-11-15] [21:50] by [Peter]
Alternative flipper driver circuitry under development with potential software control of coil-strenght.

[04-11-15] [21:47] by [Peter]
Weekly internal report distributed.

[04-11-15] [21:45] by [Peter]
Group-photo of the team.

[04-11-15] [21:44] by [Peter]
Lane-guides autocad construction finalized.

[04-11-15] [21:43] by [Peter]
First customized constructions manufactured. Finishing of surface to be executed within a week.

[04-11-15] [21:40] by [Peter]
Backbox sideart finished

[04-11-09] [08:15] by [Peter]
www.swannpinball.se is now a registered domain for the project.

[04-11-08] [09:31] by [Peter]
Switch-matrix communication-bus first tests successful.

[04-11-08] [09:30] by [Peter]
Power-engineering for Coildriving presents an Alpha version of circuitry.

[04-11-08] [09:29] by [Peter]
Side-art of Cabinett in it's final stages. The first DMD-animations created.

[04-11-08] [09:27] by [Peter]
Weekly internal report distributed.

[04-10-25] [08:58] by [Peter]
Switch-matrix prototype under construction, interface circuitry expected to be finalized this week.

[04-10-25] [08:56] by [Peter]
Major parts and mechanics has been accuired, some has been attached to the whitewood playfield and more will follow under the coming weeks.

[04-10-25] [08:53] by [Peter]
Weekly internal report distributed with news from PinballExpo. Essential mechanical parts accuired the past weeks at Expo.

[04-10-03] [23:40] by [Peter]
Weekly internal report distributed.

[04-10-03] [23:38] by [Peter]
First sketches presented of Backlight artwork.

[04-09-27] [08:13] by [Peter]
Cabinet-art expected to be finalized within the following weeks.

[04-09-27] [08:11] by [Peter]
Preparations for PinballExpo in line with schedule. Database over parts needed compiled.

[04-09-27] [08:08] by [Peter]
Weekly internal report distributed.

[04-09-25] [21:12] by [Peter]
Mechanical tests of Balldelivery from cup's to certain instancies successful.

[04-09-13] [09:38] by [Peter]
Previous weeks weekly internal report distributed. Rules sheet updated with added minor requested specialties.

[04-09-06] [14:43] by [Peter]
Voice-staging has located our first characters. Adjustments to scripts and rules will be made to better fit with these voices.

[04-09-06] [14:40] by [Peter]
First mechanical parts drawings sent away for prototype manufactoring.

[04-09-06] [14:39] by [Peter]
Previous weeks weekly internal report distributed.

[04-09-03] [09:36] by [Peter]
Audio-staging v1.0 document (restricted security level) finalized. Will be distributed to concerned individuals this weekend.

[04-09-03] [09:31] by [Peter]
Meeting with a potential hardware-supplier to be executed today.

[04-09-03] [09:28] by [Peter]
Our first ramp have been pre-engineered. Initiated work on mechanical constructions for movable parts.

[04-08-27] [14:10] by [Peter]
Weekly internal report distributed.

[04-08-22] [21:23] by [Peter]
Plastic-parts pre-engineered.

[04-08-20] [14:59] by [Peter]
Weekly internal report distributed.

[04-08-20] [07:59] by [Peter]
Limited news distributed due to a major rework is in progress.

[04-08-13] [14:33] by [Peter]
Weekly internal report distributed.

[04-08-12] [09:23] by [Peter]
Major mechanical parts order executed.

[04-08-09] [09:24] by [Peter]
Lane-guides pre-engineered.

[04-08-06] [09:47] by [Peter]
Weekly internal report distributed.

[04-08-05] [07:48] by [Peter]
Initiated work on parts database.

[04-08-04] [18:24] by [Peter]
Automagical update of News for www.tpod.org activated.

[04-07-30] [10:21] by [Peter]
Weekly internal report distributed.

[04-07-29] [14:47] by [Peter]
Slingshot artwork finished. Minor update Audio-sequencies and soundscape overview presented.

[04-07-29] [09:55] by [Peter]
Additional personal called in for Electronics-engineering. Detailed rulesheet reworked, adjustments made to help for the programming-team.

[04-07-26] [15:02] by [Peter]
About on webpage updated with information about Audio.

[04-07-25] [22:26] by [Peter]
Pre-version written of development-software for Switch-matrix I/O. Testrun executed.

[04-07-23] [09:21] by [Peter]
Weekly internal report distributed.

[04-07-22] [07:53] by [Peter]
Work on detailed Animations and layout in progress. Internal survey on layout of graphics.

[04-07-20] [13:53] by [Peter]
E-mail service is up and running. Some accounts is still having problems, expected to be solved within 48 hours.

[04-07-19] [21:35] by [Peter]
Draft of Video-sequencies partially finished, about 200 animations before cleanup.

[04-07-19] [09:37] by [Peter]
E-mail service is down. Please use tpod@lund.bonet.se for all urgent messages.

[04-07-19] [08:19] by [Peter]
Minor update on webpage. Switchmatrix first testrun successful.

[04-07-16] [15:00] by [Peter]
Initiated structuration of Video-sequencies.

[04-07-15] [12:50] by [Peter]
Weekly internal report distributed.

[04-07-14] [17:05] by [Peter]
First draft of Audio-sequencies finished, about 450 clips before cleanup.

[04-07-14] [12:54] by [Peter]
Online closed forum created to simplify communication between team-members.

[04-07-12] [12:37] by [Peter]
Skillshots and targets adjustments made in rules. Major update of audio-sequencies.

[04-07-11] [19:52] by [Peter]
Rules No-mode and Audio-quotes(1) updated. Initiated structuration of Audio-sequencies.

[04-07-09] [14:13] by [Peter]
Extended the multiplayer-section with more details.

[04-07-08] [16:33] by [Peter]
Updated Audio and Video-sequences to match current rules. Added impossible shots in cheats documentation.

[04-07-08] [12:25] by [Peter]
Weekly internal report distributed.

[04-07-07] [12:05] by [Peter]
Minor corrections and changes made on the About web-page.

[04-07-07] [08:45] by [Peter]
First draft of cable color-coding sheet.

[04-07-07] [07:50] by [Peter]
Initiated creation of multiple security levels to simplify publication and news-headlines.

[04-07-06] [16:18] by [Peter]
Updated MB7 & MB8 in rules and some minor changes for Audio-quotes(1).

[04-07-06] [13:59] by [Peter]
Team-information on webpage updated.

[04-07-04] [13:46] by [Peter]
Webpage online!

[04-06-29] [23:05] by [Peter]
First draft of online information webpage about the project created.

[04-06-29] [22:21] by [Peter]
Preparations for going online with webpage. Creation of publication guidelines.